Tower Crane Dismantling Method Statement May 2026
Tower Crane Dismantling Method Statement is a critical document detailing the step-by-step procedures to safely disassemble and remove a tower crane from a site. Since the completed structure often occupies most of the available space, dismantling is frequently more complex than erection. 1. Key Components of the Method Statement
The following safety measures will be implemented during the dismantling work: tower crane dismantling method statement
The slewing ring and cab are typically removed as one unit before the final mast sections. Phase 6: Base & Foundation The fixing angles or foundation anchors are released. The remaining base section is removed. Tower Crane Dismantling Method Statement is a critical
Step 5: Dismantle the Mast (Tower Sections)
- Two options:
- Sequence of dismantling (reverse of erection).
- Hand signals and radio protocols.
- Emergency stop and evacuation route.
- Confirmation that all personnel have valid IPAF/Lifting certificates.
Dismantling a tower crane requires a meticulous, top-down sequence—involving hook block removal, counterweight reduction, and jib disassembly—to maintain structural balance. Key safety requirements include comprehensive risk assessments, strict adherence to manufacturer manuals, and mandatory site exclusion zones. Read the full method statement at Scribd. Method Statement Dismantle Tower Crane - Scribd Two options:
Environmental Considerations
6. Dismantling Sequence (General – reverse of erection)
Note: Actual sequence depends on crane type (top-slewing, self-erecting, luffing jib). This example is for a typical top-slewing hammerhead crane.
Step 3: Dismantle the Jib (Fly Jib or Main Jib)
Using the auxiliary mobile crane.